WGB Railway Opening01
Waupaca Record
FORMAL OPENING OF THE
WAUPACA-GREEN BAY RAILWAY
CROWD OF ABOUT TWO HUNDRED
AND FIFTY GATHERS TO SEE
THE ARRIVAL OF THE FIRST
TRAIN
MUCH PRAISE IS DUE TO
PROMOTERS OF THE PROJECT
Train Arrived Here >From
The Road Is Now Prepared To handle Freight Business
Passenger Trains in a Few
Days
The
formal opening of the Waupaca Green Bay Railway took place in this city on
Wednesday morning as the special train which left
The
train consisted of an engine and coach and the official party was made up of
A.G. Nelson, president of the road and A.M. Penney, one of the directors, with
master Mechanic Radler of the Green Bay and Western and T.J. McGrath of Green
Bay, the contractor who had charge of the construction of the road.
Owing
to the balasting of a short piece of track which is occupying the attention of
Mr. McGrath at the present time, the passenger schedule will not be put into
effect for a few days but the road is ready to handle freight.
Much
praise is due the promoters of this project for their untiring efforts in
bringing to completion a work which will add so materially to Waupaca’s growth
and prosperity.
The
following passenger schedule will commence in a few days.
Trains
Leave Waupaca
No.
1,
No.
3,
No.
5,
Arrive
No. 2 at
No. 4 at
No. 6 at
Waupaca Republican
FIRST TRAIN
Passenger Coach and Engine
for
Wednesday,
January 15th, at about
The
passengers were A.G. Nelson, President; A.M. Penney, One of the Directors;
Frank Stout, Commissary Sergeant; T.J. McGrath, General Contractor and W.P.
Raidler, Master mechanic of the G.B. & Western.
A
large crowd was on hand at the depot and the band played joyous music as the
train pulled in. This was the
consummation of nearly two years of effort much of which is ancient history
outlined many times in the Republican but a few facts may be of interest in regard to
the actual construction of the road.
The
working survey, started on
Those
who are not acquainted with such tasks and have only seen the field work can
have no idea of the amount of labor involved in figuring out the cuts and
fills, the curves and grades and making the working plans and drawings. A thousand and one things of which the outsider
knows nothing at all must be exactly computed.
This work was completed and the plans submitted for bids about May first
and the contract for the construction let to the T.J. McGrath Construction
about May third. Actual construction
work began about May 18th at
In
the course of the completion of the work 125,000 cu. yds.of
dirt had to be moved; six bridges had to be built across the branch of
the Little Wolf; the sink hole at
The biggest cut was one of
27 ft. height above grade from which 11,000 cu. yds. were
taken and the biggest fill was 11 feet below grade and required 6500 cu. yds of
earth to fill.
The sink at Scandinavia
occupied 25 men for two months 500 cu yds of rock 4 acre of small tamarack
timber, 12 car loads of old ties and 8,000 cubic yards of earth went into the
sink hole proper and 6000 feet timbers were used on the approaches with many
car loads of cinder to support the track. The fill at the marl mill bridge gave
way twice because of the uneven settling.
This used up 14,000 cubic
yards of earth and delayed completion for four weeks.
They began to lay steel
about the fifth of October and completed the work the last week in
December. The cost of the road is
$120,000 apportioned about as follows:
right of way $9,000, terminals $5,000, steel $28,000, ties and other
supplies $33,000, contractor $45,000.
There are about 10 miles of main track and about a mile of side tracks
and switches.